WHEREAS,On August 28, 2012, Resolution 2012-360 awarded Project 2012-S-3,
5th Street Sanitary Sewer Improvements to Van Kirk Brothers Contracting of Sutton, Nebraska, in
the amount of$1,734,105.93; and
WHEREAS, Change Order No. 1 incorporates additional construction calendar
days into the contract; and
WHEREAS, Section A; 5th Street gravity sewer construction will add forty-five
(45) days for a completion date of September 30, 2013; and
WHEREAS, Section B; Rehabilitation of gravity sewer between 4th and 5th Street
will add thirty-one (31) days for a completion date of July 31, 2013.
NOW,THEREFORE,BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
THE CITY OF GRAND ISLAND, NEBRASKA, that authorization to proceed with additional
construction calendar days described in Change Order No. 1 with Van Kirk Contracting of Sutton,
Nebraska is hereby approved, with no additional cost to the contract.
BE IT FURTHER RESOLVED,that the Mayor is hereby authorized and directed to
execute such Change Order No. 1 on behalf of the City of Grand Island.
Adopted by the City Council of the City of Grand Island,Nebraska, July 23, 2013.