05/14/2013 Resolutions 2013-149 RESOLUTION 2013-149
WHEREAS, on October 11, 2011 Grand Island City Council, by Resolution No.
2011-307, approved the consulting agreement with Black & Veatch of Kansas City, Missouri;
for project management, collection system master planning and conceptual designs for the
Northeast Interceptor sewer, Collection System rehabilitation and Wastewater Treatment
rehabilitation in the amount of$1,121,160.00, and
WHEREAS, on April 24, 2012 Grand Island City Council, by Resolution No.
2012-111, approved Amendment No. 1 allowed for the continuation of the design effort to final
design and bidding, in the amount of$1,910,075.00; and
WHEREAS, on August 28, 2012 Grand Island City Council, by Resolution No.
2012-229, approved Amendment No. 2 to add CDBG guideline provisions, and provided for
construction engineering services for the Lift Station No. 7 Improvements and 4th Street to 5th
Street; Eddy Street to Vine Street rehabilitation, in the amount of$53,000; and
WHEREAS, on November 13, 2012 Grand Island City Council, by Resolution
No. 2012-329, approved Amendment No. 3 allowed for construction engineering services and
resident inspection during construction for the 5th Street Sanitary Sewer Improvements, as well
as for the South & West Sewer Interceptor Improvements with the consulting firm Black &
Veatch of Kansas City, Missouri, in the amount of$265,754.00; and
WHEREAS, on February 12, 2013 Grand Island City Council, by Resolution No.
2013-34, approved Amendment No. 4 allowed for the review to the "Report on Revenue
Requirements, Cost of Service and Rates for Wastewater", in the amount of$30,000; and
WHEREAS, on February 12, 2013 Grand Island City Council, by Resolution No.
2013-35, approved Amendment No. 5 allowed preliminary design engineering services in Phase
II of the North Interceptor Sewer planning, and final biding documents for Phase II-B North
Interceptor Sewer with the consulting firm Black & Veatch of Kansas City, Missouri in the
amount of$451,896; and
WHEREAS, on May 14, 2013 Grand Island City Council, by Resolution No.
2013-148, approved Amendment No. 6 allowed fee compensation in engineering services that
were not specifically identified in the original design agreement entitled "Wastewater
Treatment Plant and Collection System Rehabilitation, in the amount of$66,324; and
WHEREAS, on May 14, 2013 Grand Island City Council, by Resolution No.
2013-148, approved Amendment No. 6 allowed Consulting Engineering Construction Phase
Services, and Resident Inspection During Construction for Phase I; North Interceptor Sewer
Construction with the consulting firm Black & Veatch of Kansas City, in the amount of
$653,293; and
WHEREAS, Amendment No. 7 will provide fee compensation in engineering
services that were not specifically identified in the original design agreement entitled
Approved as to Form R .. ti, r'
May 14,2013 ° City: rney
"Wastewater Treatment Plant and Collection System Rehabilitation"; and
WHEREAS, Amendment No. 7 will provide Consulting Engineering
Construction Phase Services, Resident Inspection During Construction, and Integration
Services for Headworks Improvements Construction with the consulting firm Black & Veatch
of Kansas City, Missouri; and
WHEREAS, the agreement cost increase for Amendment No. 7 is $1,878,450,
resulting in a revised agreement cost of$6,429,952; and
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL
OF THE CITY OF GRAND ISLAND, NEBRASKA, that such Amendment No. 7 to the
agreement with Black & Veatch of Kansas City, Missouri is hereby approved.
BE IT FURTHER RESOLVED, that the Mayor is hereby authorized and directed
to execute such Amendment No. 7 on behalf of the City of Grand Island.