05/14/2013 Resolutions 2013-140 RESOLUTION 2013-140
WHEREAS, the City of Grand Island Public Works Department prepared a Project
Programming Request to the Nebraska Department of Roads for the Various Locations in Grand
Island Resurfacing Project; and
WHEREAS, such request was approved by the Nebraska Department of Roads on
April 5, 2011; and
WHEREAS,the total project cost was estimated at$2,747,266,with$549,453 being
the responsibility of the City of Grand Island; and
WHEREAS,an agreement with the Nebraska Department of Roads was approved by
Grand Island City Council through Resolution No. 2011-125 to proceed with this project; and
WHEREAS, Supplement Agreement No. 1 is necessary to show their commitment to
delivering all Local Public Agency federal aid projects,NDOR will use the August Redistribution
funds in FFY2013 and FFY2014 to provide for full federal participation for all First Class City STP
projects that are currently programmed; and
WHEREAS, individual projects are to be capped at their current estimate; and
WHEREAS, the current total estimated cost for the Various Locations in Grand
Island(Resurfacing) Project is $3,412,768. The amount of Federal STP funds obligated to date is
$290,218. The program supplemental agreement caps the amount for future obligations at
$2,537,600.
NOW,THEREFORE,BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
THE CITY OF GRAND ISLAND, NEBRASKA, that Supplemental Agreement No. 1 with the
Nebraska Department of Roads for the Grand Island Various Locations Resurfacing Project is hereby
approved; and the Mayor is hereby authorized and directed to execute such agreement on behalf of
the City of Grand Island.
Adopted by the City Council of the City of Grand Island,Nebraska, May 14, 2013.