Loading...
01/08/2013 Resolutions 2013-3 RESOLUTION 2013-3 WHEREAS, on April 10,2012,the contract was awarded by Council to Magnetech Industrial Services, Inc., of Saraland,Alabama for the major inspection and overhaul of the turbine generator at Platte Generating Station in the amount of$496,338.00; and WHEREAS,during this inspection,the bid included a base amount of 800 man-hours of repair labor for the work required on the turbine diaphragm blades; and WHEREAS,the bid also included labor rates for additions or reductions in the repair labor amount,as the amount of actual work required was not known until the unit was disassembled and inspected; and WHEREAS during the work,more extensive damage to the turbine diaphragm blades was found to need repairs, and the total additional cost to repair the turbine was $136,822.10, for a final contract amount of$633,160.10. NOW,THEREFORE,BE IT RESOLVED BY THE MAYOR AND COUNCIL OF THE CITY OF GRAND ISLAND,NEBRASKA, that Change Order#1 for the Turbine Generator Inspection and Repair for an additional amount of$136,822.10 is hereby approved. Adopted by the City Council of the City of Grand Island,Nebraska, January 8, 2013. Jn V. ricek, Mayor Attest: 9 a RaNae Edwards, City Clerk Approved as to Form a „11. January 7,2013 la City Mrney