08/12/2008 Resolutions 2008-199RESOLUTION 2008-199
WHEREAS, on May 2, 2006, by Resolution 2006-151, the City of Grand
Island awarded a bid in the total amount of $7,406,080.00 (including alternate bids 2 and
3) for the construction of a Law Enforcement Center to Chief Construction Company of
Grand Island, Nebraska; and
WHEREAS, included in the $7,406,080 bid was a construction
contingency of $150,000; and
WHEREAS, on February 12, 2008 by Resolution 2008-45 the City of
Grand Island approved substantial completion of the Law Enforcement Center with Chief
Construction changing the cost of the project to a total of $7,316,080 and reducing the
contingency allowance for the project to $24,926.45, and
WHEREAS, such changes have been incorporated into Change Order No.
21, and will reduce the contingency fund to $21,165.14.
WHEREAS, such changes have been incorporated into Change Order No.
22 and will close the contingency fund and reduce the cost of the construction project by
at total of $21,165.14
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND
COUNCII. OF THE CITY OF GRAND ISLAND, NEBRASKA, that the Mayor be, and
hereby is, authorized and directed to execute Change Order No. 21 for the construction of
the Law Enforcement Center to provide the modification set out as follows:
Close the contingency fund .............. ... + $21,165.14
Total ..................................................... + $21,165.14
Adopted by the City Council of the City of Grand Island, Nebraska, August 12, 2008.
or
Mi~tk~Jtckerso» Lo+,w~c: (~~i`~brC~Itw'f"
Attest: ,~
Paul Briseno, puty City Clerk
Approved as to Forma
August 12, 200807 City orney