09/13/2011 Resolutions 2011-243RESOLUTION 2011 -243
WHEREAS, on June 28, 2011 by resolution 2011 -155 authorized Black & Veatch
Corporation of Kanas City, Missouri to prepare engineered construction documents based on
recommendation outlined in a technical memorandum titled "Screw Pump Replacement Evaluation ", by
resolution
WHEREAS, on June 28, 2011 by resolution 2011 -155 further authorized City staff to
negotiate contractual change in work with the contracting firm Oakview dck Construction; and
WHEREAS, on August 31, 2011 city staff and engineer Black & Veatch have negotiated a
unit cost Change Order No. 2 with Oakview dck, LLC of Red Oak, Iowa at $397,897.00; and
WHEREAS, engineer Black & Veatch has reviewed the unit cost for additional
Rehabilitation of pumps (Base Work Items), Replace Lower Bearings (Alternative Work Item, and Re -Coat
Screws) (Alternative Work Item) as fair and reasonable; and
WHEREAS, uncertainty in the structural welds of the screw pumps until coating system
removal; and
WHEREAS, such change order shall provide for Rehabilitation of Pumps, Replace Lower
Bearings, and Re -Coat Screws; and
WHEREAS, after Change Order No. 2, the revised contract is $3,974,149.00; and
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF THE
CITY OF GRAND ISLAND, NEBRASKA, that Change Order No. 2 with the contracting firm, Oakview
dck, LLC of Red Oak, Iowa, in the amount of $397,897.00 for WWTP- 2010 -3 Aeration Basin
Improvements project at the Wastewater Treatment Plant is hereby approved.
BE IT FURTHER RESOLVED, that the Mayor is hereby authorized and directed to
execute such contract on behalf of the City of Grand Island.
Adopted by the City Council of the City of Grand Island, Nebraska, September 13, 2011.
Attest:
RaNae Edwards, City Clerk
Approved as to Form A
September 13, 2011 0 City Attomey