09/13/2011 Resolutions 2011-235RESOLUTION 2011 -235
WHEREAS, the Diamond Engineering Company of Grand Island, Nebraska, was
awarded the contract for Water Main Project 2011 -W -1, 7th Street from Elm Street to Clark Street,
from 7th Street to 9th Street, at the April 26, 2011 City Council meeting in the amount of
$206,907.32; and
WHEREAS, the Contract with the Diamond Engineering Company provides for the
contractor to be paid on the basis of actual quantities installed at the contract's unit prices; and
WHEREAS, due encountered unknown obstacles, adjustments were needed in actual
quantities installed versus estimated quantities, the amount was increased by $23,418.38 from the
original bid; and
WHEAREAS, Change Order #1 was prepared for the final construction contract
adjustment, resulting in a final contract amount of $230,325.70.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
THE CITY OF GRAND ISLAND, NEBRASKA, that Change Order #1 with the Diamond
Engineering Company of Grand Island, Nebraska resulting in a final contract price of $230,325.70, is
hereby approved.
Adopted by the City Council of the City of Grand Island, Nebraska, September 13, 2011.
Attest:
RaNae Edwards, City Clerk
Approved as to Form n
September 12, 2011 13 City Attorney