07/12/2011 Resolutions 2011-165RESOLUTION 2011 -165
WHEREAS, Van Kirk Brothers Contracting of Sutton, Nebraska, was awarded the
contract for Water Main Project 2009 -W -1, Cedar Street between South Front Street and North
Front Street, at the January 25, 2011 City'Council meeting in the amount of $178,172.30; and
WHEREAS, the Contract with Van Kirk Brothers Contracting provides for the
contractor to be paid on the basis of actual quantities installed at the contract's unit prices; and
WHEREAS, due to minor adjustments in actual quantities installed versus estimated
quantities for the project, and alternate construction methods and materials, the cost of the project
was reduced $2,989.24 from the original bid.'
WHEAREAS, Change Order #1 was prepared for the final construction contract
adjustment, resulting in a final contract amount of $175,183.06.
NOW, THEREFORE, BE IT RESOLVED BY THE MAYOR AND COUNCIL OF
THE CITY OF GRAND ISLAND, NEBRASKA, that Change Order #1 with Van Kirk Brothers
Contracting of Sutton, Nebraska resulting in a final contract price of $175,183.06, is hereby
approved.
Adopted by the City Council of the City of Grand Island, Nebraska, July 12, 2011.
Attest:
RaNae Edwards, City Clerk
Approved to Form n �
July 11, 2011 1 0 City Attorney